Frequently Asked Questions
About Permits
Q. How do I apply?
-
Complete application (Application can be obtained on line or at the Township Office)
- Submit site plan (location of new or additional structures on property showing approx. dimensions)
-
Submit detailed construction plans, including:
-
Obtain septic design and application approval for new construction or for additional bedrooms or bathrooms from the Ontario Health Unit 1-800-267-8260.
-
Obtain entrance approval from County or Township Roads Departments
-
Pay permit fee
Q. What else should be considered?
Bell Canada - location of phone cables
Gas- location of lines
Hydro - permits for electrical inspections, location of existing and future services
Insurance - coverage during construction
Heritage Buildings - review by LACAC
Q. What is expected during construction?
Post permit: keep set of plans available
Notify inspector 48 hours before pouring footing, backfilling, completion of framing, plumbing, heating, fireplace rough-in, vapour barrier, insulation and final inspection
Q. Why do I need inspections?
Inspections are a service paid by you through the permit fee. Proper inspections will ensure the site is safe and meets the Building & Fire Codes. This will protect your investment and maintain a standard or development for the municipality.
Q. What happens if I don't get a permit?
Building without a permit is against the law and is subject to fines or penalties as set out in the Building Code Act.
Q. I am looking to install a pool or inflatable pool.
Do I need a permit?
Yes, a permit is required, contact the building Department for any questions about pools.